Pearl Exploration and Production Ltd.



Operational Updates


OPERATIONS UPDATE -- THIRD QUARTER 2008


Mooney Heavy Oil Project -- Alberta

As of the end Q3 2008 Pearl has drilled ten net horizontal wells in our Mooney area thus far in 2008. Four of the eight wells were drilled as part of the polymer pilot which will consist of two polymer injection wells and two producers. Regulatory approval has been obtained for the polymer pilot and polymer injection began in late October of 2008. Preliminary results from the pilot are expected by Q1 2009. Plans for a field wide polymer flood implementation are expected to be finalized by Q2 2009 with the initiation of full field implementation targeted as early as Q4 2009.

In addition we have continued to advance the conversion of the field to a water flood project. During Q3 an additional 1.5 sections were approved for water flood with water injection expected to commence in late Q4 2008 and early Q1 2009.

In addition, one additional section is awaiting waterflood approval which is expected to commence water injection in Q1 2009. The water flood will ultimately assist in both maintaining production levels and increasing reserves as recoveries are expected to increase with the demonstration of pressure maintenance, a decreasing gas/oil ratio ("GOR") and sustained production. In the event that the polymer pilot is successful the investment in the infrastructure implemented for the water flood will be used as base infrastructure for the polymer flood. While the Company expects that the implementation of the water flood will result in both sustained production and higher reserve recovery, in the short term as the field is converted there will be intermittent production disruption in Mooney.

The Company was successful at a crown land sale acquiring 6 sections (1536 hectares) of land at 100% working interest in the Mooney core area.

The Mooney field produced approximately 1,650 Boed during Q3. Production from Mooney was curtailed significantly for approximately nine weeks, beginning at the end of June by approximately 700 Boed. This shut-in was a result of our pipeline provider, on short notice, terminating our ability to ship solution gas that contained higher than permitted CO2 on their system. To rectify the situation we procured, installed and commissioned an amine plant in less than 10 weeks. As a result we now have the capability to remove excess CO2 from our gas stream which allows us to ship our gas production to market without interruption to service.

Onion Lake Heavy Oil Project -- Saskatchewan

In Onion Lake the Cyclic Steam Stimulation (CSS) thermal pilot continues. The first well ("Z1") has completed the first steam and production cycles, with a peak rate of over 150 Bopd being achieved. The Z1 well began its second injection cycle September 21/08. Steam injection on the second well ("Z2") began on June 20th and the first production cycle commenced on August 11, 2008. Mechanical issues were experienced during the steam cycle on the Z2 well resulting in a small amount of steam entering the reservoir. As a result, the first production cycle of the Z2 well was lower than expected. It is anticipated that the Z2 well will perform similarly to the Z1 well when similar amounts of steam have been injected into the reservoir. We are currently preparing to begin the second steam cycle in the Z2 well.

During Q3 production from Onion Lake average approximately 2,300 Boed; this excludes production from the CSS thermal pilot as net revenue from the pilot is captured as an offset to the net capital costs for that project.

Blackrod Heavy Oil Project -- Alberta

At Blackrod, as previously announced the Company closed a transaction on August 20th to acquire an additional 30% working interest in the Blackrod project area. The company paid $4.5 million in cash and, if successful, will be required to make additional payments totaling up to $11 million, based on pre-set criteria of success. In September and early October the Company was also successful at 2 separate crown land sales and acquired an additional 36 sections (9,216 net hectares) of oil sands leases contiguous to our project area. Subsequent to the end of Q3 the Company entered into an agreement with Serrano to increase our working interest in the original project area from 65% to 80% in return for the disposal of our interests in Serrano and a carried work program of net $5 mm over the next twelve months.

Pearl intends to continue its plan to drill 10 to 15 stratigraphic core wells in the 2008/2009 winter to further delineate this deposit and gather additional petrophysical and reservoir fluid characteristic data. The application for the required governmental approvals of the thermal SAGD pilot project was submitted in May of 2008 and is expected to be approved in the next 6 to 12 months.

There is currently no production at Blackrod and we do not anticipate any production coming from Blackrod until our pilot project is operational. We currently anticipate the pilot being operational in 2010.

San Miguel Heavy Oil Project -- Maverick Basin, South Texas

At San Miguel, Pearl and its 50% partner TXCO continued steam injection at the Steam Assisted Gravity Drainage ("SAGD") pilot located within the Chittim "B" Lease. Production, temperature, and pressure monitoring of the well pair continue to confirm that the well pair has entered SAGD mode with initial oil flows being observed.

At Saner Ranch, the pilot facility construction is proceeding on schedule with mechanical completion still expected to be completed in early December. The Saner Ranch pilot includes a vertical inverted five spot well pattern and a horizontal three well pattern that both utilize a modified Fracture Assisted Steamflood Technology ("FAST") process. Steam injection into the vertical inverted five spot pattern commenced on August 28 as part of the reservoir warm-up phase with initial indications of connectivity being observed within the inverted 5 spot pattern. The three horizontal wells were completed in September and achieved first steam injection / reservoir warm-up phase as scheduled on October 8, 2008. Preliminary performance results from both patterns are anticipated during the first half of 2009.

By the end of the second quarter of 2009, Pearl expects to be in a position to select which of the three recovery techniques will be used to form the basis of a commercial development project, SAGD or one of the two modified FAST techniques. In addition, work continues on the commercial aspects of a successful project in San Miguel including the method in which the JV will generate energy to produce steam and the markets and value of the production from the project.

The is currently no commercial production in San Miguel and we do not anticipate any commercial production originating from San Miguel until the JV moves into a commercial development of this resource. We have begun to see early production in the Chittum pilot in October.

Other Properties -- Alberta, Saskatchewan

In order to enhance the value of certain non-core assets, Pearl initiated a 9 well drilling program at Ear Lake, Salt Lake and Druid in Q3, which is now complete. All of these wells will initiate production in Q4. Overall, the production increase from this program is expected to reach between 400 and 500 bopd by year end.

Production from other non-core Canadian properties averaged 1,800 Boe/d in Q3. It is still the intention to sell these properties once market conditions improve.

Other Properties -- U.S.

The Company also holds interests in several other areas in the United States, including Queen City gas fields, the West Rozel and Gunnison Wedge in Utah, Promised Land and Fiddler Creek in Montana and Queen City gas field in Texas. There is limited or no production from these areas and there are only minor evaluation plans contemplated for these lands in 2008. However, the Company believes certain of these lands contain large resource potential and may, based upon further evaluation, be developed in the future.

In September, we agreed to dispose of our land and tangible interests in the Palo Duro basin to Tyner Resources Ltd. ("Tyner") in exchange for an equity interest in Tyner. This transaction is consistent with our strategy to focus on our 4 core areas and is expected to close prior to year-end.


OPERATIONS UPDATE -- SECOND QUARTER 2008

OPERATIONS UPDATE -- FIRST QUARTER 2008

OPERATIONS UPDATE -- FIFTH QUARTER

OPERATIONS UPDATE -- FOURTH QUARTER

OPERATIONS UPDATE -- THIRD QUARTER

OPERATIONS UPDATE -- SECOND QUARTER 2007

 



Adnet Communications Inc.